McGill University has mandated Ardec Construction Inc. to carry out the following project: Montreal Neurological Institute / 18-121 - Cyclotron aerial exhaust.

The project consists of installing the aerial conduit to replace the existing one at the Montreal Neurological Institute hospital.

Project manager: Eric Boutet, CIMA+ - eric.boutet [at] cima.ca ">eric.boutet [at] cima.ca 

Assistant project manager: Allison Ly, CIMA+ - allison.ly [at] cima.ca 

Construction start date: September 22, 2023

Planned construction end date: November 1, 2023

Work schedule: Mondays to Fridays, 6 a.m. to 4 p.m.

Scope of work:

Exterior: Installation of the ventilation duct on the roof and on the side of the Penfield wing.

Impact:

  • The interior courtyard will be inaccessible for vehicles.
  • Emergency exit doors remain functional. People will be able to exit the interior courtyard via a pedestrian path.