News

Construction Start: McCall MacBain Arts - Masonry work

Aerial view of McCall MacBain building
Published: 7 June 2024

Please be advised that McGill University has mandated Rainville et Frères to carry out the following project: 19-163 McCall MacBain Arts – Masonry work.

Final phase of the masonry restoration on two facades of the west side of the McCall MacBain Arts Building.

Construction start date: June 17th, 2024

Planned construction end date: September 17th, 2024

Work schedule: Monday to Friday, 6 a.m. to 3 p.m.

Project Manager: Jocelyn Blanchet - jocelyn.blanchet [at] gph-inc.com

Assistant Project Manager: Pierre Beauchamp - pierre.beauchamp [at] gph-inc.com

Contact for building users: Erin McDonagh, Associate Building Director - erin.mcdonagh [at] mcgill.ca

Scope of work:

  • Installation of protective structures where required.
  • Installation of scaffolding over the roof of the adjacent building (Leacock) and on the front façade of the Arts Building.
  • Use of a crane to load new stones onto the scaffolding.
  • Installation of new stones and completion of masonry joints.
  • Cleaning of façades and removal of temporary installations.

Impact & mitigation:

  • There will be increased traffic of trucks around the work site. Signallers will be present to control circulation during stone loading operations.
  • Protective structures will be installed over the west entrance of the Arts Building and over the east exit of the Leacock Building
  • Pedestrians will not be able to cross from the Arts Building to the Leacock Building but will rather have to walk around the Redpath Museum to reach the Leacock Building.
Back to top