Sylvan Adams Sports Science Institute

Important: Several street closures are planned as part of other construction projects underway in the vicinity. To remain updated, be sure to check the New Vic website for all details.

Partial street closure on Pine Ave.: Between May 13 and May 24, 2024 (inclusively), one of the two westbound lanes on Pine Ave. will be closed between Aylmer St. and University St.

Rendering of the front of the new SASSI project on Pine Avenue

Construction start: December 2022

Planned construction end: December 2024

Budget: $42,501,000

As part of the creation of the Sylvan Adams Sports Science Institute, announced on August 31, 2022, McGill University will transform four of its row houses on Pine Avenue into a complex comprising state-of-the-art testing labs, training suites, research offices, and meeting rooms. The row houses are located between the Montreal Neurological Institute and the Sir Arthur Currie Memorial Gymnasium.

The project consists of building a back extension to the four row houses and an adjoining fifth house, and restoring a large part of their overall existing volume as well as the four front façades. Necessary upgrades to bring the facility up to building codes, including for seismic resistance and universal access, are also planned as is the replacement of the HVAC, electrical and water distribution systems.

More information on the Sylvan Adams Sports Science Institute: mcgill.ca/sassi

What to expect

Date Work Impact
Fall 2022 - Fall 2023 Selective demolition and excavation, replacement of underground services, structural work

Increased vehicle traffic to and from construction site, including cranes and large vehicles

Medium to high levels of noise, particularly close to the site

Pedestrian traffic possibly restricted to south sidewalk for a limited period of time

Pedestrian traffic possibly restricted to south sidewalk

Fall 2023 - Fall 2024 Interior work, structural work Increased circulation of vehicles to and from construction site
Fall 2024 Asphalting in the back of the facility and landscaping

Asphalt odours

Work happening exclusively within the site perimeter

 

Back to top